Capital Paving Projects Now Underway
The following is the tentative road maintenance schedule for the coming weeks. Please note that all work is weather dependent and dates may change if conditions require.
June 29th
- Lyn Valley Road & Kitley Line 8 (Patching)
- Kilkenny Road (Tight Blading)
June 30th
- Coon's Road & Tincap (Items 7–10) (Paving)
- Lyn Valley Road & Halleck's Road North (Tight Blading)
July 1st
No work scheduled: Canada Day
July 2nd
- Tincap, Heather Crescent, Meg Avenue, Bronze Avenue & Susan Drive (Paving)
- Kitley Line 8 (Tight Blading)
July 3rd
- Applewood Circle & Old Sharpes Lane North (Paving)
July 6th
- Maplewood Drive, Paul Road, Wanda Drive & Eleanor Fulford Crescent (Paving)
- Kilkenny Road (Shouldering)
July 7th
- Lyn Valley Road & Halleck's Road North (Shouldering)
July 8th
- Kitley Line 8 (Shouldering)
Following the completion of this work, the next phase of road maintenance, including micro surfacing, will begin. Additional scheduling information will be shared as it becomes available.
Thank you for your patience as these road improvements are completed. Please use caution when travelling through work zones and obey all posted signage and directions from on-site crews.
Sign up to our news and notices
Stay up to date on the Township's activities, events, programs and operations by subscribing to our news and notices.